Location

UWS, Manhattan, NY

 

Scope

Gut renovation of a 2,0000 Sq. ft. two bedroom, two bath Upper West Side pre-war
co-op with custom cabinetry and luxury finishes.

 

Metrics

Our homeowner had a Complete Project Spend of $221 PSF and we scheduled 27 weeks for design and 22 weeks for build. The result was achieved with a Price Variance of 0% and a Schedule Variance of 0%. 

Full project metrics available in person.

Team

Screen Shot 2018-11-06 at 3.20.22 PM.png

Architect
Agustin Ayuso

Screen Shot 2018-11-23 at 11.22.19 AM.png

Build Manager
Aaron Borenstein

Screen Shot 2018-11-06 at 5.08.28 PM.png

Job Captain
Walter Sweiconek